Lamar Utilities Board meeting of November 24, 2026
Barbara Crimond | Nov 23, 2026 | Comments 0
After approving the meeting minutes from the November 10, 2026 meeting, Purchase Orders 2025-08118 through 2025-08329 were approved. These totaled $60,356.83. The largest purchase order for this billing period was for $26,062.45 to Tri County Ford for engine and exhaust work. Bills totaling $664,545.16 were approved for payment. $572,869.92 to ARPA for power purchase was the largest amount of this total.
Superintendent Hourieh’s System Operating Report stated that through the end of October, the wind turbines have generated 8,860.80 MWH’s of electricity. This is about 24.02% higher than the same period last year. The turbines have an average capacity factor of 28.68% which is higher than last year by about 0.33%. When compared individually, T-3 ranked first, followed by T-1. T-4, ARPA’s turbine, generated 3,699.96 WWH’s. The Springfield turbine generated 5,019.61 MWH’s of electricity through the same period with an average capacity factor of 45.96%. The line crew completed the installation of 1,010 feet of underground line in McClave. The new line will power a 1,000 kva, 277/480v padmount transformer for the McClave School Campus. They also installed a 37.5 kva pole mount transformer and upgraded a secondary service line Hartman to improve loading balance and prevent overload conditions. The crew is in the process of installing Christmas lights along Main Street, East Olive Street and the Welcome Center area.
The Board met in an Executive Session to receive legal advice regarding matters affecting the electric utility industry and to discuss recent communications with the City of Lamar’s legal counsel before adjourning.
By: Barbara Crimond
Filed Under: City of Lamar • Featured • Utilities
About the Author: