Main Street Construction Progress Report

 

South Main Street

ACC Mountain West is concurrently working on Phases l & lll on the US Highway 287 reconstruction project through Main Street Lamar. The work consists of installation of a new waterline system, storm drainage system and concrete paving between Park Street and Canal Road.

Construction Project Between Park and Oak Streets

Phase l, located between Park and Oak Streets will maintain one lane of thru traffic in each direction during construction.

There will be a switch in that traffic flow from the EAST side to the WEST side after concrete pavement and curb and gutter work has been completed on the West side, later next week (November 7, 2017).

The speed limit through the construction area is 25mph and crews will be on site from 7am to 7pm, Monday through Friday. During the Thanksgiving holiday, work will be shut down from Wednesday, November 22nd through Sunday, November 26th.

Filed Under: City of LamarConsumer IssuesFeaturedPublic SafetyTourismTransportationUtilitiesWeather

Tags:

About the Author: